NEW QUESTION # 85
Project team leaders can influence team performance by developing:
- A. detailed project management processes.
- B. respect, shared values and trust.
- C. a clear stakeholder management plan.
- D. important political alliances.
Answer: B
NEW QUESTION # 86
Which of the following is a reason for scheduling?
- A. To establish the roles and responsibilities of the project team.
- B. To produce the quality acceptance criteria.
- C. To establish what work needs to be performed.
- D. To produce a project management plan.
Answer: C
NEW QUESTION # 87
Who is primarily responsible for configuration management in the project?
- A. Quality manager.
- B. The project team.
- C. Risk manager.
- D. Project manager,
Answer: D
NEW QUESTION # 88
What is the main benefit of using a risk register in the project?
- A. It records risk ownership and how issues are being managed.
- B. It directs the team in how the management of risk in the project should be conducted.
- C. It assesses the impact and probability of risks taking place.
- D. It records risks. their impact and the responses being adopted.
Answer: D
NEW QUESTION # 89
Which one of the following statements best describes resource scheduling?
- A. A. process that identifies when resources are needed.
- B. A. process to assign roles to project resources.
- C. A. process to estimate the project resources.
- D. A. process which identifies activities that will need project resources.
Answer: A
NEW QUESTION # 90
We have an expert-written solution to this problem!
Who has ultimate responsibility for project risk?
- A. Steering group.
- B. Project manager
- C. Risk owner.
- D. Project sponsor.
Answer: D
NEW QUESTION # 91
Which of the following would be considered part of a configuration management process?
- A. Planning. auditing. monitoring, controlling, closing.
- B. Planning, identification, controlling, status accounting, auditing.
- C. Scheduling, baselining, controlling, responding, closing.
- D. Initiating, identifying, assessing, planning, responding.
Answer: B
NEW QUESTION # 92
When effectively implemented, what is one of the key roles of governance?
- A. Provide confidence that the business case is the best option for the current circumstances and that there will be no changes as the project is being delivered.
- B. Provide confidence to all stakeholders that projects are being well managed and the most appropriate financial and technical controls are being exerted.
D Provide confidence to all project team members that their jobs are secure at least from the period of the project start to the handover. - C. Provide confidence that the plans that have been developed will guarantee that the project will be delivered on time and to budget.
Answer: B
NEW QUESTION # 93
One purpose of a typical project business case is to:
- A. analyse cost-benefit of the project.
- B. plan project work packages
- C. carry out earned value analysis.
- D. allocate resources to the project.
Answer: A
NEW QUESTION # 94
Governance could best be defined as:
- A. the framework of authority and accountability that defines and controls the outputs, outcomes and benefits from projects, programmes and portfolios.
- B. the framework that structures a review of the project, programme or portfolio and aids a decision to be made about whether to continue with the next phase or stage of progress.
- C. the framework that is used for selection, prioritisation and control of an organisation's projects and programmes in line with its strategic objectives and capacity to deliver D the framework used by the organisation and approved by the project board at project initiation that allows the definition of the terms of reference for the project.
Answer: A
NEW QUESTION # 95
What would be a most likely result for an organisation following a PESTLE analysis?
- A. The organisation would most likely have a number of options available as to how the desired objectives could be achieved.
- B. The organisation would have an understanding of the necessary skills required to deliver the objectives required.
- C. The organisation would know what political change is most likely and therefore the impacts on objectives considered.
Answer: A
Explanation:
D The organisation would be able to develop an accurate estimate of the costs and time frame for the objectives to be achieved.
NEW QUESTION # 96
Which one of the following would be expected to form the main part of a risk analysis?
- A. Deciding on how to respond to the risk and who should implement the response.
- B. Deciding if the risk is a threat or opportunity.
- C. Evaluating the risk in terms of severity and relative importance.
- D. Deciding on the approach to project risk management.
Answer: C
NEW QUESTION # 97
One disadvantage of physical communication is:
- A. that your body language may not reflect what you're saying when passing on information
- B. it is reliant on technology being available to all relevant members of the project.
- C. that no audit trail is available for review at a later date by project team members.
- D. its significant environmental impact when compared to other forms of communication.
Answer: D
NEW QUESTION # 98
If using an iterative life cycle what actions might be necessary for scope items that are NOT considered as
'must have'?
- A. They need to be given a special priority to ensure that they are definitely delivered.
- B. They should have best resort to ensure they efficiently delivered.
- C. They would sacrificed if at any time Was to go over budget or be late
- D. The project could be If the delivery of these requirements were proving more difficult than expected
Answer: C
NEW QUESTION # 99
When using a PESTLE analysis, a potential change in national government would be an example of a:
- A. economic factor.
- B. sociological factor.
- C. political factor.
Answer: C
Explanation:
D A. potential change of government would not be considered in such an analysis.
NEW QUESTION # 100
When using a PESTLE analysis, a potential change in national government would be an example of a:
- A. economic factor.
- B. potential change of government would not be considered in such an analysis.
- C. sociological factor.
- D. political factor.
Answer: D
NEW QUESTION # 101
What is one of the most important aspects to establish about a stakeholder's interest in the project?
- A. If it is positive or negative.
- B. If it is regular or intermittent.
- C. If it is influenced by the project.
- D. If it is influenced by other stakeholders.
Answer: A
NEW QUESTION # 102
......
APM APM-PFQ Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
| Topic 6 |
|
| Topic 7 |
|