AACE International is a professional association that provides resources and support to professionals in the field of cost engineering and project management. One of the certifications offered by AACE International is the Planning & Scheduling Professional (PSP) certification. The PSP certification is designed for professionals who specialize in project planning and scheduling, and demonstrates a level of knowledge and expertise in these areas.


AACE International is a globally recognized professional association for the management and development of cost and schedule professionals. The organization provides a variety of professional certifications, including the AACE-PSP (Planning & Scheduling Professional) certification, designed for professionals who specialize in project scheduling, planning, and control.

 

NEW QUESTION # 59
Which of the following are NOT normally included in the project scope statement, either directly or by reference?

  • A. Project deliverables
  • B. Project objectives in terms of cost, schedule and quality measures
  • C. Project justification
  • D. Project contract between the contractor and owner

Answer: C


NEW QUESTION # 60
What owner action could have mitigated the late completion of the project?

  • A. Prepare better structural steel drawings.
  • B. Hire a more senior project manager.
  • C. Self-perform more of the work.
  • D. Use a procurement agent to monitor and expedite equipment deliveries.

Answer: D


NEW QUESTION # 61
Which of the following is NOT true?

  • A. Remaining durations can exceed original durations.
  • B. A network must contain only one Critical Path.
  • C. Multiple calendars can affect the total float calculation.
  • D. Constraints can interfere with the longest path calculation.

Answer: A


NEW QUESTION # 62
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

  • A. Different calendars are assigned to certain activities in the logical chain.
  • B. The schedule has too much detail to reflect an accurate critical path.
  • C. The schedule is projecting an "early completion".
  • D. Certain activities in the critical path have no successors.

Answer: D


NEW QUESTION # 63
The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.

  • A. Budgeted cost of work performed (BCWP)
  • B. Budgeted cost of work scheduled (BCWS)
  • C. Estimate at completion (EAC)
  • D. Budget at completion (BAC)

Answer: D


NEW QUESTION # 64
Which of the following is NOT input data to the construction planning process?

  • A. Input from the contractor
  • B. Bonding capacity of subcontractors
  • C. The contract
  • D. Input from the owner

Answer: B


NEW QUESTION # 65
At the end of month one, did the delay to the parking structure foundation delay the project?

  • A. NO.
  • B. Yes, by 9 calendar days.
  • C. Yes, by 4 calendar days.
  • D. Yes, by 14 calendar days.

Answer: C


NEW QUESTION # 66
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

  • A. 1 crane
  • B. 4 cranes
  • C. 3 cranes
  • D. 2 cranes

Answer: D


NEW QUESTION # 67
What is the free float for Activity F?

  • A. 2month.
  • B. 1months.
  • C. 3 months.
  • D. 0months.

Answer: D


NEW QUESTION # 68
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

  • A. Delay product release by 5 days.
  • B. Delay manufacturing by 5 days.
  • C. Expedite printing by 5 days.
  • D. Expedite packaging by 5 days.

Answer: A


NEW QUESTION # 69
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

  • A. The project plans and specifications
  • B. The project geotechnical report
  • C. The government's report on future high-clearance bridge projects
  • D. The regulations published by the government aviation agency

Answer: C


NEW QUESTION # 70
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

  • A. The delay must affect the critical path.
  • B. The delay must affect the contractor's planned construction schedule.
  • C. The delay must not cause monetary harm to the defendant.
  • D. The delay must be concurrent with the delay attributable to both parties.

Answer: A


NEW QUESTION # 71
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

  • A. 5 days
  • B. 6 days
  • C. 8 days
  • D. 4 days

Answer: B


NEW QUESTION # 72
An earned value-based project control system can use either of which two budgets as the basis of its calculations?

  • A. Earned or budgeted cost yearly.
  • B. Labor hours or dollars.
  • C. Linear feet or dollars.
  • D. Direct or indirect cost.

Answer: A


NEW QUESTION # 73
What is the relationship depicted between Activity G and Activity H?

  • A. Finish-to-start.
  • B. Start-to-start.
  • C. Finish-to-finish.
  • D. You cannot tell with the supplied information.

Answer: B


NEW QUESTION # 74
Activity C is a

  • A. Contentious activity.
  • B. Continuous activity.
  • C. 1-day activity.
  • D. Milestone.

Answer: D


NEW QUESTION # 75
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

  • A. 48 lifts
  • B. 30 lifts
  • C. 24 lifts
  • D. 36 lifts

Answer: D


NEW QUESTION # 76
......


AACE International AACE-PSP (Planning & Scheduling Professional (PSP)) Exam is a globally recognized certification for professionals who are responsible for planning and scheduling in various industries. Planning & Scheduling Professional (PSP) Exam certification is offered by AACE International, a professional association that provides education, certification, and networking opportunities to project control professionals. The AACE-PSP certification evaluates the knowledge, skills, and abilities of candidates in planning, scheduling, and controlling projects.

 