AACE International is a professional association that provides resources and support to professionals in the field of cost engineering and project management. One of the certifications offered by AACE International is the Planning & Scheduling Professional (PSP) certification. The PSP certification is designed for professionals who specialize in project planning and scheduling, and demonstrates a level of knowledge and expertise in these areas.
AACE International is a globally recognized professional association for the management and development of cost and schedule professionals. The organization provides a variety of professional certifications, including the AACE-PSP (Planning & Scheduling Professional) certification, designed for professionals who specialize in project scheduling, planning, and control.
NEW QUESTION # 59
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
- A. Project deliverables
- B. Project objectives in terms of cost, schedule and quality measures
- C. Project justification
- D. Project contract between the contractor and owner
Answer: C
NEW QUESTION # 60
What owner action could have mitigated the late completion of the project?
- A. Prepare better structural steel drawings.
- B. Hire a more senior project manager.
- C. Self-perform more of the work.
- D. Use a procurement agent to monitor and expedite equipment deliveries.
Answer: D
NEW QUESTION # 61
Which of the following is NOT true?
- A. Remaining durations can exceed original durations.
- B. A network must contain only one Critical Path.
- C. Multiple calendars can affect the total float calculation.
- D. Constraints can interfere with the longest path calculation.
Answer: A
NEW QUESTION # 62
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
- A. Different calendars are assigned to certain activities in the logical chain.
- B. The schedule has too much detail to reflect an accurate critical path.
- C. The schedule is projecting an "early completion".
- D. Certain activities in the critical path have no successors.
Answer: D
NEW QUESTION # 63
The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.
- A. Budgeted cost of work performed (BCWP)
- B. Budgeted cost of work scheduled (BCWS)
- C. Estimate at completion (EAC)
- D. Budget at completion (BAC)
Answer: D
NEW QUESTION # 64
Which of the following is NOT input data to the construction planning process?
- A. Input from the contractor
- B. Bonding capacity of subcontractors
- C. The contract
- D. Input from the owner
Answer: B
NEW QUESTION # 65
At the end of month one, did the delay to the parking structure foundation delay the project?
- A. NO.
- B. Yes, by 9 calendar days.
- C. Yes, by 4 calendar days.
- D. Yes, by 14 calendar days.
Answer: C
NEW QUESTION # 66
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
- A. 1 crane
- B. 4 cranes
- C. 3 cranes
- D. 2 cranes
Answer: D
NEW QUESTION # 67
What is the free float for Activity F?
- A. 2month.
- B. 1months.
- C. 3 months.
- D. 0months.
Answer: D
NEW QUESTION # 68
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
- A. Delay product release by 5 days.
- B. Delay manufacturing by 5 days.
- C. Expedite printing by 5 days.
- D. Expedite packaging by 5 days.
Answer: A
NEW QUESTION # 69
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.
- A. The project plans and specifications
- B. The project geotechnical report
- C. The government's report on future high-clearance bridge projects
- D. The regulations published by the government aviation agency
Answer: C
NEW QUESTION # 70
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
- A. The delay must affect the critical path.
- B. The delay must affect the contractor's planned construction schedule.
- C. The delay must not cause monetary harm to the defendant.
- D. The delay must be concurrent with the delay attributable to both parties.
Answer: A
NEW QUESTION # 71
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?
- A. 5 days
- B. 6 days
- C. 8 days
- D. 4 days
Answer: B
NEW QUESTION # 72
An earned value-based project control system can use either of which two budgets as the basis of its calculations?
- A. Earned or budgeted cost yearly.
- B. Labor hours or dollars.
- C. Linear feet or dollars.
- D. Direct or indirect cost.
Answer: A
NEW QUESTION # 73
What is the relationship depicted between Activity G and Activity H?
- A. Finish-to-start.
- B. Start-to-start.
- C. Finish-to-finish.
- D. You cannot tell with the supplied information.
Answer: B
NEW QUESTION # 74
Activity C is a
- A. Contentious activity.
- B. Continuous activity.
- C. 1-day activity.
- D. Milestone.
Answer: D
NEW QUESTION # 75
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?
- A. 48 lifts
- B. 30 lifts
- C. 24 lifts
- D. 36 lifts
Answer: D
NEW QUESTION # 76
......
AACE International AACE-PSP (Planning & Scheduling Professional (PSP)) Exam is a globally recognized certification for professionals who are responsible for planning and scheduling in various industries. Planning & Scheduling Professional (PSP) Exam certification is offered by AACE International, a professional association that provides education, certification, and networking opportunities to project control professionals. The AACE-PSP certification evaluates the knowledge, skills, and abilities of candidates in planning, scheduling, and controlling projects.
AACE-PSP Sample Practice Exam Questions 2024 Updated Verified: https://www.dumpsreview.com/AACE-PSP-exam-dumps-review.html
Pass Key features of AACE-PSP Course with Updated 120 Questions: https://drive.google.com/open?id=12B_w6XEUhCUQReK_-3mSYuEzYhItO0CA