Latest [Sep 24, 2021] AACE International AACE-PSP Exam Practice Test To Gain Brilliante Result
Take a Leap Forward in Your Career by Earning AACE International AACE-PSP
NEW QUESTION 49
What is the remaining work duration of Active D?
- A. 3.
- B. 8.
- C. 0
- D. 4.
Answer: D
NEW QUESTION 50
A driving relationship is _____________________.
- A. A finish-to-start relationship.
- B. A critical relationship.
- C. The link between two related activities.
- D. The link between a predecessor and the activity whose dates it controls.
Answer: D
NEW QUESTION 51
In a "crashed" schedule, which is a chain of activities that precede activity 2004?
- A. 1001, 2002, 2003
- B. 1001, 2001, 2002, 2003
- C. 2001, 2002, 2003, 2007
- D. 1001, 2002, 2002, 2003, 3001
Answer: B
NEW QUESTION 52
Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?
- A. Testing, Manufacturing and Packaging.
- B. Printing the Manual.
- C. Packaging only.
- D. Drafting and Proofing the Manual.
Answer: A
NEW QUESTION 53
Which activity is drawn in the incorrect position?
- A. Activity D.
- B. Activity E.
- C. Activity C.
- D. Activity G.
Answer: A
NEW QUESTION 54
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?
- A. 06-04-02.
- B. 06-05-02.
- C. 06-11-02.
- D. 06-18-02.
Answer: B
NEW QUESTION 55
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.
PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the
"normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.
Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?
- A. $524,000.
- B. $307,000.
- C. $420,000.
- D. $552,000.
Answer: D
NEW QUESTION 56
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT
- A. Look at each activity independently and don't follow specific logic paths when assigning activity durations.
- B. Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.
- C. Use gross building square footages. The pluses and minuses all average out.
- D. Use the people responsible for performing the work as a resource to assign activity durations.
Answer: C
NEW QUESTION 57
Determine the driving activity for Activity 10001.
- A. There is no driving activity for Activity 10001 in the backward pass.
- B. Activity 10002.
- C. Activity 11001.
- D. Activity 9005.
Answer: B
NEW QUESTION 58
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.
- A. Estimate at completion (EAC)
- B. Estimate to complete (ETC)
- C. Budget at completion (BAC)
- D. Budgeted cost of work performed (BCWP)
Answer: B
NEW QUESTION 59
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
- A. B.
- B. C.
- C. W.
- D. S.
Answer: D
NEW QUESTION 60
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
- A. The delay must not cause monetary harm to the defendant.
- B. The delay must affect the critical path.
- C. The delay must affect the contractor's planned construction schedule.
- D. The delay must be concurrent with the delay attributable to both parties.
Answer: B
NEW QUESTION 61
How much Total Float does drafting the product manual have?
- A. 5 workdays.
- B. 0 workdays.
- C. 10 workdays.
- D. 15 workdays.
Answer: C
NEW QUESTION 62
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
- A. Historical production rates
- B. Black-Scholes model
- C. Time impact analysis
- D. The Eichleay formula
Answer: A
NEW QUESTION 63
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
- A. Expedite packaging by 5 days.
- B. Delay manufacturing by 5 days.
- C. Delay product release by 5 days.
- D. Expedite printing by 5 days.
Answer: C
NEW QUESTION 64
Each of the following accurately describes total float in a schedule EXCEPT:
- A. Can be positive or negative.
- B. The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.
- C. Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.
- D. The amount of time an activity can be delayed without delaying the overall project completion time.
Answer: B
NEW QUESTION 65
What owner action could have mitigated the late completion of the project?
- A. Use a procurement agent to monitor and expedite equipment deliveries.
- B. Prepare better structural steel drawings.
- C. Self-perform more of the work.
- D. Hire a more senior project manager.
Answer: A
NEW QUESTION 66
What is the free float for Activity F?
- A. 0months.
- B. 1months.
- C. 3 months.
- D. 2month.
Answer: A
NEW QUESTION 67
What problems can a soils engineer deal with on a project?
- A. Survey error.
- B. Archeological findings.
- C. Hidden subsurface conditions.
- D. Toxic soils.
Answer: C
NEW QUESTION 68
Which is NOT an industry-recognized methodology for quantifying critical delay?
- A. Time Impact.
- B. Gantt Chart.
- C. Periodic Windows.
- D. Collapsed As-Built.
Answer: B
NEW QUESTION 69
Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?
- A. 12-17-03 and 4 days of float
- B. 12-18-03 and 25 days of float
- C. 12-18-03 and 4 days of float
- D. 12-27-03 and 24 days of float
Answer: A
NEW QUESTION 70
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
- A. 09-08-01.
- B. 09-15-01.
- C. 09-18-01.
- D. 09-28-01.
Answer: A
NEW QUESTION 71
......
Authentic Best resources for AACE-PSP Online Practice Exam: https://www.dumpsreview.com/AACE-PSP-exam-dumps-review.html
Updates Up to 365 days On Developing AACE-PSP Braindumps: https://drive.google.com/open?id=1BSdgExgbU3A0-YkxjLRg6xbGS05jJQQY

